Follow our progress on Scandic Court II
EXTERNAL WORK
Electricity and light installation is complete.
AUGUST 2021
Interior work is complete.
EXTERNAL WORK
Barb wire and fence installation is completed.
INTERIOR & EXTERNAL WORK
Installation of handrails is completed.
INTERIOR & EXTERNAL WORK
Window fabrication and installation is completed.
INTERIOR WORK
POP ceiling installation is completed – Third floor
INTERIOR WORK
Internal wall screeding and tiles installation – First and second floor
EXTERNAL WORK
External wall plastering in progress.
ROOF FORMWORK
Third floor
ROOF BEAMS CASTING
100% completed – Third floor
LINTEL BEAM FORMWORK
Lintel beam formwork – 100% Completed
ROOF BEAM FORMWORK
Third floor
BLOCK SETTING PREP
Third floor
SLAB CASTING - DAY 2
Third floor
OCTOBER 2020
First floor wall plastering / M&E.
AUGUST 2020
Second floor slab concrete and block setting.
JUNE 2020
First Floor Covering.
MAY 2020
Preparing first floor works, after a Covid-19 pause in works.
NOVEMBER 2019
Pile Cup works begin.
SEPTEMBER 2019
Breaking of the pile cups.
JULY 2019
Preparatory work for piling (12m depth)
June
Blockwork for pile groups was done (11 of 37).
INTERNAL WORK
Interior work is complete.
JUNE 2021
External work is complete.
EXTERNAL WORK
Ground floor for parking flooring is complete.
APRIL 2021
Wall painting is complete.
EXTERNAL WORK
Wall plastering is complete.
FEBRUARY 2021
Construction of the gates – Ground floor
M&E
M&E installation fittings – Third Floor
JANUARY 2021
THE ROOF IS 100% COMPLETED – Third Floor
ROOF CARCASS
Installation of the roof carcass – Third Floor
DECEMBER 2020
Roof beams casting – Third Floor
LINTEL BEAM FORMWORK
Third Floor
NOVEMBER 2020
Lintel Beam Casting – Third Floor
COLUMN REINFORCEMENTS
Third Floor
SLAB CASTING
Third floor
SEPTEMBER 2020
Third floor form-work and reinforcement.
JUNE 2020
First floor block setting.
MAY 2020
Mounting work.
FEBURARY 2020
Ground floor.
OCTOBER 2019
Pile Column works
JULY 2019
Piling in process
JUNE 2019
Land filling works
June
The blinding and block work for a pile group were done (12 of 37)