fbpx

Follow our progress on Scandic Court II

EXTERNAL WORK

Electricity and light installation is complete.

AUGUST 2021

Interior work is complete.

EXTERNAL WORK

Barb wire and fence installation is completed.

INTERIOR & EXTERNAL WORK

Installation of handrails is completed.

INTERIOR & EXTERNAL WORK

Window fabrication and installation is completed.

INTERIOR WORK

POP ceiling installation is completed – Third floor

INTERIOR WORK

Internal wall screeding and tiles installation – First and second floor

EXTERNAL WORK

External wall plastering in progress.

ROOF FORMWORK

Third floor

ROOF BEAMS CASTING

100% completed – Third floor

LINTEL BEAM FORMWORK

Lintel beam formwork – 100% Completed

ROOF BEAM FORMWORK

Third floor

BLOCK SETTING PREP

Third floor

SLAB CASTING - DAY 2

Third floor

OCTOBER 2020

First floor wall plastering / M&E.

AUGUST 2020

Second floor slab concrete and block setting.

JUNE 2020

First Floor Covering.

MAY 2020

Preparing first floor works, after a Covid-19 pause in works.

NOVEMBER 2019

Pile Cup works begin.

SEPTEMBER 2019

Breaking of the pile cups.

JULY 2019

Preparatory work for piling (12m depth)

June

Blockwork for pile groups was done (11 of 37).

INTERNAL WORK

Interior work is complete.

JUNE 2021

External work is complete.

EXTERNAL WORK

Ground floor for parking flooring is complete.

APRIL 2021

Wall painting is complete.

EXTERNAL WORK

Wall plastering is complete.

FEBRUARY 2021

Construction of the gates – Ground floor

M&E

M&E installation fittings  – Third Floor

JANUARY 2021

THE ROOF IS 100% COMPLETED – Third Floor

ROOF CARCASS

Installation of the roof carcass – Third Floor

DECEMBER 2020

Roof beams casting – Third Floor

LINTEL BEAM FORMWORK

Third Floor

NOVEMBER 2020

Lintel Beam Casting – Third Floor

COLUMN REINFORCEMENTS

Third Floor

SLAB CASTING

Third floor

SEPTEMBER 2020

Third floor form-work and reinforcement.

JUNE 2020

First floor block setting.

MAY 2020

Mounting work.

FEBURARY 2020

Ground floor.

OCTOBER 2019

Pile Column works

JULY 2019

Piling in process

JUNE 2019

Land filling works

June

The blinding and block work for a pile group were done (12 of 37)